Date : 28/8/08
Venue : Sijangkang
Guys .....Land clearing is already 80% done although some obstacles that we faced.... let me share some of the pics..Mr B thanks for your visit last week..although you were having fever.....
Wak Aziz "the tukang man" is testing the soil.
The mangrove woods for the piling
In the centre of the farm
View from the centre....
Discussion with Wak Aziz ...look at the watery area...it was raining in the morning.
This are the frame structures of the mushroom house "roofing" part
Tiang steel bar
Ok guys time is limited and we are going to speed up the project a.s.a.p......we will update you hope next few days....bye and take care SALAM....